11. Midsummer Common: Feasibility Study

Drainage Ditch: Could This Be a New Wetland Habitat?

The aim of the project was to determine whether an old drainage ditch on Midsummer Common could be opened-up to create a new wetland habitat.  

Service checks came back all clear, but the test dig revealed that the assumed drainage ditch was dry and therefore impractical for wetland creation. 

Contractors undertaking a test dig to determine if water was present in the drainage ditch.   

The test dig revealed no water was present in the drainage ditch, so it is unsuitable for wetland creation.

The test dig revealed that the assumed drainage ditch contained only wiring. Consultations are ongoing with local residents and stakeholders to determine next steps.    

Dates 2021-2022
StatusComplete  
Area of habitat created or improved  
LocationMidsummer Common, Cambridge

Partners and Funders

Funded by: Natural England’s Nature Recovery Programme.